Earned Value measurement using MS Project
- Create a project by listing the activities (WBS), enter durations, define dependencies along with appropriate leads and lags etc.
- Define resources with Standard Rate in Resource Sheet. Assign value $1 if resource costs are not to be shared
- Assign resources to each activities.
- Baseline the Project to get BAC i.e., baseline cost/Budget At complete/total project cost
- During tracking stage, as you update the progress values (update Actual Start, Actual Finish, Remaining work values instead of updating %complete value)
- In order to examine the EVM values, refer View --> Table --> More Tables --> Earned Value / Earned Value with Cost Indicators / Earned Value with Schedule Indicators tables by setting the Status Date (Project --> Project Information --> Status Date)
Labels: MS Project - EVM
0 Comments:
Post a Comment
Subscribe to Post Comments [Atom]
<< Home