Best Practices for Schedule Planning
Following are few best practices to be followed while developing schedule in MS Project
- Define holidays
- Define resource vacations
- Define resource availability (with start/finish end dates, work load (whether resource is available 50%/100%) for the project
- Avoid over/under allocation of resources
- Define Milestone tasks
- Make use of deadline date option for tasks instead of ‘Finish no later than’ or ‘Must Finish on’ constraints
- *Do not* assign resources at Summary task level
- *Do* Assign resources only at task level
- You should only link *like tasks* - for example, subtasks to subtasks and summary tasks to summary tasks.
- planned work / effort for a task should not be more than 40 hours (for effective tracking)
planned duration for a task should not be more than 5 days - Ensure all tasks have successor or predecessor values
- Establish parallelism/overlapping between tasks using (FS – x) / SS / FF days tasks (eg., FS-3 days/SS/SS+2/FF-2 days etc)
- Avoid assigning flexible / semi-flexible constraints / hard coded dates to tasks
- Avoid assigning multiple resources to tasks for effective identification of responsible/accountable task owner
- Use recurring task feature for meeting tasks
- Consider review/rework effort
- Configuring ‘Project Start Date’, which avoids introducing ‘Start No Earlier Than’ constraint for most of the tasks (Most of entry level PMs does this mistake with lack of knowledge)
Labels: MS Project - Bestpractices
0 Comments:
Post a Comment
Subscribe to Post Comments [Atom]
<< Home