Satya's blog

Tuesday, October 27, 2009

Best Practices for Schedule Planning

Following are few best practices to be followed while developing schedule in MS Project
  • Define holidays
  • Define resource vacations
  • Define resource availability (with start/finish end dates, work load (whether resource is available 50%/100%) for the project
  • Avoid over/under allocation of resources
  • Define Milestone tasks
  • Make use of deadline date option for tasks instead of ‘Finish no later than’ or ‘Must Finish on’ constraints
  • *Do not* assign resources at Summary task level
  • *Do* Assign resources only at task level
  • You should only link *like tasks* - for example, subtasks to subtasks and summary tasks to summary tasks.
  • planned work / effort for a task should not be more than 40 hours (for effective tracking)
    planned duration for a task should not be more than 5 days
  • Ensure all tasks have successor or predecessor values
  • Establish parallelism/overlapping between tasks using (FS – x) / SS / FF days tasks (eg., FS-3 days/SS/SS+2/FF-2 days etc)
  • Avoid assigning flexible / semi-flexible constraints / hard coded dates to tasks
  • Avoid assigning multiple resources to tasks for effective identification of responsible/accountable task owner
  • Use recurring task feature for meeting tasks
  • Consider review/rework effort
  • Configuring ‘Project Start Date’, which avoids introducing ‘Start No Earlier Than’ constraint for most of the tasks (Most of entry level PMs does this mistake with lack of knowledge)

Labels:

0 Comments:

Post a Comment

Subscribe to Post Comments [Atom]

<< Home