Identifying split tasks in MPP
Create Text field with the following formula to identify split tasks.
IIf(ProjDateDiff(Start,Finish,"standard") >[Duration],"Split","No Split")
Above formula assigns value of “Split” or “No Split” to the text field depending on the task property.
Contributed by my Wipro colleague: Satpreet Singh.
IIf(ProjDateDiff(Start,Finish,"standard") >[Duration],"Split","No Split")
Above formula assigns value of “Split” or “No Split” to the text field depending on the task property.
Contributed by my Wipro colleague: Satpreet Singh.
Labels: MS Project - Split tasks